Once Aqua confirms service is available and there is a main in front of your property, you will be asked to submit water service application(s), a site plan, and review related documents for the requested services to
PaNewWaterConnections@AquaWater.com.
4. Aqua will review and provide comments or request changes to the submitted documents
- Allow 10-15 days for service application review and approval
5. Aqua will provide the applicant named in section A of the application with an approval letter for the connection to Aqua’s water Main. The letter will include the contact information for an Aqua representative so the applicant can schedule a site meeting to discuss the following:
- Review and determine the service installation location(s), meter box/vault specifications and location, and backflow protection requirements
- All new construction requires metering to be in an Aqua approved enclosure
6. Aqua will apply for any road opening permits and schedule the installation of the service connections from the water main to the right of way line/the property line. (This step may vary by location- details will be provided in the approval letter).
7. The property owner will be responsible for hiring a plumber to install the water line and meter box/vault on their property.
8. Aqua will inspect the meter box/vault, and once approved will schedule for the he meter installation.
9. Aqua will turn on the water to the property at the Aqua owned curb valve and Customer billing will begin.
Frequently Asked Questions:
How can I learn if Aqua PA water is available for my project location?
- Submit a Request for Water Service for information about water availability. Include the property address, municipality name and county. If an address is not assigned to the lot, provide a tax parcel number and neighboring address with the nearest intersecting street. Aqua will typlically respond in 3-5 days.
How can I obtain a “Will Serve Letter” for my project?
- Submit a Request for Water Service and check the box for WILL SERVE LETTER REQUEST. Include the project’s full address, municipality, county and a map or plan of the site. Include details of the project. For example: new construction, renovation, increase in service size, relocation, etc. Response time is 5-7 days.
My project requires a fire sprinkler system, but I do not have a contractor selected for the installation. Can I just leave the section about the designer information blank until I hire one?
- Aqua PA requires the name and credentials of the engineer who calculated the size of fire line. That information must be provided on any fire water service application.
Who makes the service connection on the water main (wet tap) and how long does it take?
- Aqua PA will arrange for the water service connection on the main, apply and pay for any road opening permits (local and state), and restore the roadway. Timelines vary depending on state highway permitting and/or your contractor’s schedule.
I want to connect to Aqua PA, but I want to keep my private well active also. Why do I need a testable backflow device on the new Aqua PA service line?
- Aqua PA must ensure our water supply is protected from cross-contamination with other water sources. A testable backflow device must be installed and tested annually if the well is still active.